10/1/25 Compactor Update
The compactor bin has been replaced. Residents may resume using the compactor as usual.
9/30/25 Roadwork & Compactor Update
Sarver paving will be here on 10/3/25. Some of the work may extend into 10/4/25. We were notified that the compactor was not compacting on 9/29/25. It was determined that the bins auto dialer feature did not initiate a call for pick up. We were informed that someone would be sent out on 9/30/25 to replace the bin. We apologize for any inconvenience this has caused you. We will continue to follow up on this matter until we have a fresh bin for our residents.
9/9/25 Roadwork Update
Sarver paving did a number of repairs today all around CLA. They were to return tomorrow to complete repairs but there has been a change of plans. They will return tomorrow to sweep the roads but must wait until Monday 9/15 to return for the rest of the repairs. The board discussed the needs of Acuminata yesterday evening and have come up with a plan of action. Due to the extensive damage on that road, we are going to chip and seal it this year to protect any microcracks from taking on water, freezing and blowing out more. of the road. We will budget for the bigger repairs to occur next year out of the road fund. We will ensure we get bids in early in the year to make sure we are scheduled for the repairs as soon as possible for the season.
9/5/25 Roadwork Update
On 9/9-9/10 Sarver Paving will be completing phase 1 of 3 for roadwork. Phase one is repairs. Please anticipate single lane construction patterns for roadwork on the following roads- Cinnamon Drive, Laurel Dr, Brandy, Coriander, Tarragon. Phase two is chip & seal which we anticipate to occur ~1-2 weeks following repairs. Phase three is the redevelopment and chip & seal of the following cul-de-sacs Cayenne, Kinata and Madrona. The third phase will have two parts. Part one is the redevelopment that will occur mid fall. Part two is chip & seal that will occur in the spring. Due to the extensive damage to Acuminata we are reviewing the best course of action for this road with our project manager and will provide on update on this road next week.
9/3/25 New yard waste disposal method update
Starting today 9/3/25 the CLA dump trailer will be placed at the rear entrance of the maintenance yard on Minosa Drive. It is for compostable materials only (grass, leaves, garden debris, compostable bags). Please do not dispose of plastic, sticks, metal, or trash. DO NOT PUT ON THE GROUND.
9/1/25 Roadwork Update
Sarver Paving will be in CLA this week to map out the repairs that will occur on 9/9/25
8/30/25 Roadwork Update
Sarver Paving will be here on 9/9/25 to complete the repairs portion of the road project. There are culverts that will be done as well as chip & seal work but that will occur on a different date. Be on the lookout for a list of general areas that repairs will occur on. Should be confirmed next week.
8/24/25 Compactor Update
The compactor bin arrived sooner than expected! Maintenance and Chris got the compactor up and running for us to begin using tomorrow 8/25/25. We are awaiting a code pad to be placed on the unit so in the meantime open the door, place your household trash inside and shut the door. The compactor will start after the door is opened and closed 3 times * Yay energy efficiency!
8/23/25 Upcoming Road Work and Waste Disposal Reminders
Sarver Paving has been approved to complete road repairs and maintenance before winter. Project dates and specific road names will be announced soon. A new compacter bin is expected to arrive next week. Until then, please use the open-top dumpsters in the office parking lot for household trash. Once repaired, the CLA dump trailer will be placed at the rear entrance of the maintenance yard on Minosa Drive. It is for compostable materials only (grass, leaves, garden debris, compostable bags). Please do not dispose of plastic, sticks, metal, or trash.
8/21/25 It’s great to see the team effort put toward the compactor project, really pay off! We are so close! We hope to have the new compactor up and running next week.
8/20/25 Huge shout out to the maintenance crew and Chris (Vice President) on their efforts with the compactor project! The maintenance crew did the prep work for the concrete pad and Chris is doing the electrical.
8/20/25 Roadwork Update
At the August board meeting we accepted a bid for the necessary road repairs. The following cul-de-sacs will be re-developed: Cayenne, Madrona & Kinata. We will soon release a more detailed list of the roads that are being repaired and an anticipated start date.